Site Clean Up
100% Complete

General site clean up, removal of trees and cutting of long grass

Earthworks
100% Complete

The earthworks involve all the bulk cut and fill works to bring the stage to the designed finished surface level.

Sewer & Drainage
100% Complete

The sewer works are the first item completed after Earthworks as it is typically the deepest service. This involves the construction of the sewer pipelines, the authorities maintenance structures and individual lot connections.

The drainage typically follows sewer and involves the construction of the drainage pipes and pits to ensure the stage will drain efficiently.

Water & Gas
100% Complete

Water and gas usually share a trench due to their close proximity and are constructed at a similar time. The construction involves the installation of pipework, valves, hydrants and individual lot connections.

Subgrade
100% Complete

Subgrade is considered the road base and is critical to the future performance of the road. It is made up of the subgrade (natural clay or engineered fill), capping layers and crushed rock layers.

Kerb & Channel
100% Complete

The kerb and channel is the concrete edging of the asphalt designed to catch stormwater flow and direct it into the drainage system.

Electrical & NBN
100% Complete

The electrical and NBN services are the last services to be constructed as they are typically the shallowest. This involves the construction of the “pit and pipe” for each service.

Footpaths & Asphalt
100% Complete

This is the final clean up portion of the works with all the finish touches constructed and installed.During this phase of works you will see concreters constructing footpaths, asphalt crews layer the base, intermediate and wearing course asphalt and bobcats spreading topsoiling across lots and nature strips.

Construction Complete
100% Complete

This indicates that construction is now compete and that Statement of Compliance (SOC) is now underway. See the SOC process below.

Construction Timeline STAGE 1 & 2

0%

100%

100%

Statement of Compliance

  • KEY
  • Pending
  • Complete
  • CIVIL CONSTRUCTION COMPLETE
  • STREET SIGNS, LINE MARKING, WEARING COURSE
  • WATER & SEWER TESTING
  • POWERCOR ELECTRICAL AUDIT
  • COUNCIL PC WALKOVER
  • VALUATION CAN BE ORDERED
  • ALL AUDITS PASSED
  • SOC FEES PAID TO EXTERNAL AUTHORITIES
  • SOC CONSENT RECEIVED IN SPEAR – ALL AUTHORITIES
  • SUBDIVISION LODGED FOR REGISTRATION
  • TITLES RECEIVED BOOK SETTLEMENTS
CONSTRUCTION UPDATE